Después de separar los paneles de tierra y misiles en la fachada por primera vez, se llama corte rapidopara hidrógeno líquido línea de alimentación de combustiblelos equipos ahora han reemplazado los sellos en el Sistema de lanzamiento espacial ([{» attribute=»»>SLS) rocket’s core stage associated with the liquid hydrogen leak detected during the Artemis I launch attempt on September 3.
Both the 8″ line used to fill and drain liquid hydrogen from the core stage and the 4″ bleed line used to redirect some of the propellant during tanking operations were removed and replaced this week.
Coming up next, technicians will reconnect the umbilical plates and perform inspections over the weekend. After that, they’ll begin preparing for a tanking demonstration as soon as Saturday, September 17. This demonstration will allow engineers to verify the new seals under cryogenic, or supercold, conditions that are expected on launch day, before proceeding to the next launch attempt.
During the operation, teams will practice loading liquid hydrogen and liquid oxygen in the rocket’s core stage and interim cryogenic propulsion stage. They will work at getting to a stable replenish state for both propellants. Teams will confirm the leak has been repaired. They will also perform the kick-start bleed test and a pre-pressurization test to validate that the ground and flight hardware and software systems can perform the necessary functions required to thermally condition the engines for flight. Teams will review the test results and develop strategies for the next launch opportunity after analyzing the data.